ATCO McIntyre Utilitity Upgrade - Summer Construciton Schedule

ATCO will be completing the next stages of the McIntyre Subdivision Utility Upgrade in summer/fall 2017. ATCO has contracted Castle Power Line Contractors and the focus for 2017 is McClennan road, McCrimmon Crescent, O'Brien Place, O'Brien Road, and Murphy Road. There are still some outstanding work on Hanna and McCandless that wasn’t completed in 2016 that will be added to the scope for 2017.


ATCO does a doorknob message drop when they are moving onto a street or street section.


The tentative schedule is May 1 – October 17, 2017.


1) Pre-construction walk through on May 2, 2017
2) Most of the temporary overhead powerline on Hanna and McCandless will be salvaged first. The overhead powerline on the south side of McCandless will remain until further notice.
3) Stage 4 - new underground construction on Murphy Road
4) Stage 3 - new underground construction on O’Brien Road & O’Brien Place
5) Stage 3 & 4 - salvage of the temporary overhead powerline O’Brien Road/Place and Murphy Road
6) Stage 1 - new underground construction and the salvaging of the temporary overhead powerline on McClennan Road
7) Stage 2 – new underground construction and the salvaging of the temporary overhead powerline on McCrimmon Crescent
8) Clean up